wiki:20_rdc_charger:35_commissioning:02_power_plant
Differences
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
wiki:20_rdc_charger:35_commissioning:02_power_plant [2023/03/31 10:07] – removed - external edit (Unknown date) 127.0.0.1 | wiki:20_rdc_charger:35_commissioning:02_power_plant [2023/05/26 13:04] (current) – external edit 127.0.0.1 | ||
---|---|---|---|
Line 1: | Line 1: | ||
+ | ====== Power plant connection ====== | ||
+ | The power plants can be connected to the grid in two ways: | ||
+ | |||
+ | |< 700px >| | ||
+ | ^ serial with grid power sensor | ||
+ | | {{ wiki: | ||
+ | |||
+ | When configuring the power plant, select | ||
+ | | ||
+ | | ||
+ | Power plants are configured as internal by default. | ||
+ | |||
+ | Obtaining data (power, voltage, etc...) from power plants is possible in two ways:\\ | ||
+ | 1. adding [[wiki: | ||
+ | 2. connecting PV inverter via Modbus TCP (for SolarEdge inverters only) | ||
+ | |||
+ | === EVSE and PV inverter connection === | ||
+ | |||
+ | |< 700px >| | ||
+ | | {{ wiki: | ||
+ | |||
+ | Add inverter using configurator: | ||
+ | * | ||
+ | {{wiki: | ||
+ | * | ||
+ | {{wiki: | ||
+ | |||
+ | |||
+ | Setup Modbus TCP on Inverter side using SolarEdge SetApp: | ||
+ | * | ||
+ | * RS485-1 -> Protocol -> SunSpec (Non-SE Logger) | ||
+ | * RS485-1 -> Device ID, enter address 1 | ||
+ | * Modbus TCP -> Enable | ||
+ | * set TCP port -> 502 | ||
+ | |||
+ | **Note**:\\ The TCP server idle time is 2 minutes. In order to leave the connection open, the request should be made within 2 minutes.\\ | ||
+ | First, add inverter to Configurator, |